Sprint Velocity & Burndown
Scope burning down across the parallel-build window toward the i4F demo on Oct 12, 2026, with per-wave velocity and pace against the straight-line ideal. Project-tracking state — the cockpit's picture of its own delivery.
Days to i4F demo
42
6w 0d · Oct 12, 2026
Scope burned down
98%118 / 120
2 remaining
Avg velocity
10tasks / wave
17 waves done · 1 in progress
Sprints complete
7/ 8
Burndown
Remaining scoped tasks per build wave (solid) against the straight-line ideal (dashed) — to the Oct 2026 demo.
Velocity per wave
Tasks burned down each build wave (bars), against the ideal burn rate of ~10/wave (dashed). Amber = under pace.
Per-wave velocity
Toggle between tasks closed each wave and pace against the straight-line ideal.
| Wave | Remaining | Ideal | Closed |
|---|---|---|---|
| Found | 120 | 120 | 0 |
| B1 | 108 | 110 | 12 |
| B2 | 90 | 100 | 18 |
| B3 | 78 | 90 | 12 |
| B4 | 70 | 80 | 8 |
| B5 | 63 | 70 | 7 |
| B6 | 54 | 60 | 9 |
| B7 | 45 | 50 | 9 |
| B8-10 | 33 | 40 | 12 |
| WaveD | 24 | 30 | 9 |
| WaveE | 14 | 20 | 10 |
| Deploy | 9 | 10 | 5 |
| Fixes | 2 | 0 | 7 |
Sprint plan
The seven-sprint march from rails to dress rehearsal. Status mirrors TASKS.md.
| Sprint | Weeks | Goal | Status |
|---|---|---|---|
| S0Sprint 0 — Rails | wk0 | Monorepo, base packages, local stack, CI. | Done |
| S0.5Sprint 0.5 — Dev-Admin Dashboard | wk0 | The PM cockpit (this app) — built first. | Done |
| S1Sprint 1 — Event spine + Creative entry | wk1–2 | Ovals, yin-yang, event/node/role + DRAFT→STAFFING gate. | Done |
| S2Sprint 2 — Validation (6 gates) + readiness | wk3–4 | Resource Capacity + Schedule Conflict gates, Ought-ness Grid. | Done |
| S3Sprint 3 — Channels, tasks, vendor, Nuggets | wk5–6 | Realtime channels, instruction versioning, click-to-move nuggets. | Done |
| S4Sprint 4 — Alerts + ack ladder + Health Timeline | wk7–8 | In-app alerts, 6-level ladder, Event Health Timeline. | Done |
| S5Sprint 5 — Mission Control Action Board | wk9 | Recommended Actions, LIVE gate, responsive role views. | Done |
| S6Sprint 6 — Harden + dress rehearsal | wk10 | STAGING deployed & live (62.169.27.202); event pages render real seeded data. Open: roles 404, real GoTrue login, readiness 0%. | In Progress |