Overview
One-screen executive summary of the Uploz build — what exists, how far along it is, and what could still move the i4F demo date.
At a glance
Workspace size and the single deadline everything burns down to
2
Apps
web · dev-admin cockpit
9
Packages
shared workspace libs
24
Migrations
schema 0001–0024 applied
612
Tests
Vitest suites green
42
Days to demo
i4F · 2026-10-12
Progress
Each ring is derived from a done / total count — honest at every value
MVP01 sprints
7/8
S0–S5 + S0.5 shipped; S6 in dress-rehearsal
Build waves
17/18
parallel agent bursts complete
RTM coverage
58/64
requirements with code + tests
Top risks
Highest-impact open items, with the status of each mitigation
No founders’ Linux server yet
HighSelf-hosted Supabase + PROD deploy are compose-ready but cannot run the live dress rehearsal until the server lands.
Sprint 6 / devops
E2E only proven on native Postgres
MediumGate keystone verified without Docker; the full Kong→PostgREST→RLS path still needs one green run on the deployed stack.
Wave E / quality
HE / HI translation fill incomplete
LowEN is complete; Hebrew and Hindi strings are scaffolded but need a native pass before the demo audience.
frontend / i18n